The changes to Putney Bridge junction have cleared their final approval, and work to move the pedestrian crossing on the bridge starts on 1 December.
Transport for London (TfL), which has to approve every junction with traffic lights in London, has signed off the council’s design, according to a letter the council sent to residents this week. TfL is due to switch on the new lights in early March.
The crossing on the bridge moves to the centre of the junction. That gives drivers turning left out of Lower Richmond Road onto the bridge about 42 seconds of green every time. At the moment, whenever someone presses the crossing button, that green drops to 25 seconds. The small traffic island on Lower Richmond Road goes as well.
The council says the most disruptive work will be done at night where possible, and temporary traffic lights will be kept off the road for most of the job. They will be needed for two nights in February, and for the last two weeks in early March, when TfL switches on the new signals.
The first job, from 1 December, is moving a CCTV pole and reshaping the kerbs on the island at the foot of the bridge. Work on the pedestrian islands carries on into the new year, and the new signal equipment goes in during February. The council puts the cost at about £450,000, including temporary traffic management and design fees.
TfL’s agreement was the final hurdle to the changes following the council’s Cabinet approval on 12 October. As recently as 12 November, council leader, Cllr Robert Morritt, said it had “been pushing TfL to make these layout and signal changes as quickly as possible”.
TfL also approved the 2024 layout, then ran the lights on timings that did not match the approved model.
Tonight, the council’s transport committee looks at moving £100,000 of TfL money, taken from a signals scheme on Wimbledon Road that is no longer going ahead, to pay for the work. The council has also asked TfL for £200,000 in all, across this year and next, and has not said whether that is part of the £450,000 or on top of it. The Cabinet decides on 9 December.
What people on foot lose
Crossing at the foot of the bridge goes back to three stages instead of two, the layout the 2024 redesign replaced. The council’s own Cabinet paper said the crossing “will revert back to a three-stage crossing as previous”.
The shorter crossing was one of the few things the 2024 design got right. A review the council commissioned in mid-2025 found more people crossing the junction than in 2021, and fewer crossing on a red man. The council said that was likely down to the bigger islands and the shorter waits.
A year ago, the officer who has led the junction work defended that crossing. Asked at the council’s transport committee in November 2025 why officers would not support going back to the old layout, Henry Cheung said the old islands had been small, narrow and crowded, so people crossed against the lights. The crossing on the bridge itself, he said, was “one of the biggest changes to the current scheme”.
When councillors backed the move in September, officers told them some pedestrians “may choose to ignore and not follow the prescribed route”.
This week’s letter to residents says the new design keeps “the number of crossings and larger islands for pedestrians”. It does not explain how that fits with a three-stage crossing.
The council looked at reopening the old tunnel under the bridge, which runs from St Mary’s churchyard beneath the road, for people on foot. According to council officers, it was “just not cost viable”. No figures have been published.
Putney.news is looking at other ways of getting people across and under the bridge, and will report on them.
March is the test
Early March is when everything done since the summer is meant to pay off. The extra lanes on Putney Bridge Road and the High Street, the island gone from outside Snappy Snaps and the wider road by the TK Maxx bus stop all lead up to the new timings.
The council itself is waiting on them: its September Cabinet paper said it would hold off deciding what to do about rat-running through Disraeli Road, Werter Road and Chelverton Road, and the roads off Putney Bridge Road, “until the effects of the traffic signal changes have been observed”.
No one has said what “fixed” would look like. The council has set no target for journey times or queue lengths to judge them against. Cllr Morritt said last week that the summer changes “have already helped”. He gave no figure. The council has also not said what it will measure once the new lights are on, or when it will publish the results.
Its junction page still says it aims to consult residents on stopping queue-jumping through side streets “in May or June 2026”. That was a consultation that never came. The same page describes the cyclists’ left turn from Putney Bridge Road onto the High Street as both brought back and suspended.
Putney.news put a number of questions to the council on Tuesday, including when TfL gave its approval and what it will measure after March.
The new lights go on in early March. That is when Putney finds out whether any of it has worked.
What happens next
The council’s transport committee meets tonight at 7.30pm at Wandsworth Town Hall, and the meeting is shown live on the council’s webcast. Work at the junction starts on 1 December, and TfL is due to switch on the new lights in early March. The council posts updates on its junction page. Questions and complaints about the works go to the council’s traffic team at trafficandengineering@wandsworth.gov.uk. If a site is badly run, here is how to report works.