‘You let it languish into dystopia’: Alton residents confront councillors over their estate

Their MP says the money is there. The council says the gap is more than £47m
A tower block on the Alton Estate in Roehampton

Alton estate residents filled a Wandsworth Town Hall committee room on Wednesday night to plead with councillors not to tear up the regeneration plan they voted for.

“For 20 years we’ve lived with promises made and promises broken,” Joanna Playford, who lives on the estate, told the Housing Overview and Scrutiny Committee. “What you, our politicians, have done is let it languish into dystopia.”

The council is going ahead with one part of the plan: a single block at the entrance to the estate, known as Block A, with 55 council homes. The rest of the regeneration, which 82.4% of voting residents backed in a ballot last year, will now come in phases. No dates are attached to them. Residents voted yes and got no.

Residents arrived wanting to know why. The council’s answer is in a paper they are not allowed to read.

Joanna Playford speaking at the Wandsworth Council Housing Committee
Joanna Playford speaking on behalf of Alton residents

The paper nobody can see

The figures behind the decision sit in a confidential appendix, kept out of the public meeting. It sets out how much City Hall awarded the council towards new council homes. The public papers say only that Wandsworth got 40% of what it bid for.

“Your papers talk a lot about the funding situation yet you lack the decency to share any figures,” Ms Playford said. “These are in a secret paper. Where is the transparency?”

Cllr Matthew Corner, the Conservative Cabinet Member for Housing, insisted the figure was not being kept back by choice. City Hall has put it under an embargo, and he was “actually frustrated” by that: he would have liked the committee to discuss it in public, “but the rules are the rules”.

Residents also felt they had been told last. The plans first appeared on the council’s Facebook page a week before the meeting, they said. Cllr Corner’s answer was that they had been published properly, in the committee’s papers.

The Cabinet takes its decision on 9 December. Councillors were told the embargo should have lifted by the time this committee next meets, towards the end of January, so residents will see the figure about seven weeks after the decision it explains. Putney.news has asked the council for it under freedom of information law.

Fleur Anderson, Putney’s Labour MP, had urged residents to come, and she brought an answer to the money question: it is there. Most of it, she told the committee, sits in the council’s housing account, which is kept separate from the general budget the government has squeezed. If the council could find £4.5m a year for extra police officers, she argued, and had saved money by scrapping 111 homes on the Ashburton estate and 81 on the Lennox, it could find it for the Alton.

“Please do not break this up,” she said. “You will not be proud of this decision.”

Cllr Corner’s reply was that nothing was being abandoned and the ballot was not being overturned. The problem, as he set it out, is money: a funding gap of more than £47m, building costs at record highs, and a government cut of £154m over three years that he called the equivalent of a 40% cut in the council’s spending power. The Ashburton and Lennox plans went, he added, because residents there did not want them. The rest of the Alton must now wait for a survey of every council home in the borough.

Fleur Anderson MP speaking at the Wandsworth Council Housing Committee
Fleur Anderson MP

Decades waiting

The Alton has been promised renewal for most of two decades.

A Conservative masterplan won approval from City Hall, then was shelved after Labour took the council in 2022. Labour replaced it with the Alton Renewal Plan in 2024 and put that to residents, who voted yes in autumn 2025 on a turnout of 41.5%. In May the Conservatives returned to run the council, and both sides have been blaming each other since.

The sharpest exchange of the night was over that ballot. Cllr Corner turned to Cllr Aydin Dikerdem, Labour’s Cabinet Member for Housing at the time, and asked why Labour had gone ahead with “a huge financial gap in the plans”.

“The Alton has never been about viability,” Cllr Dikerdem replied. Labour had chosen to invest in a place neglected for decades: “The viability gap was known and we still went ahead because we believed in that project.”

When Cllr Corner said it was unfortunate the gap “was not shared with residents at the time”, Cllr Dikerdem cut in. It had been shared, he said, with the councillors taking the decision. It just “wasn’t front and centre” of the marketing of the plans.

In fact the Landlord Offer residents voted on, a 19-page booklet, does not mention the gap at all; its only sums of money are the payments to people whose homes would be knocked down, marking it as a shameful admission, and a shameful defence of the previous administration.

Cllr Dikerdem was the councillor in charge. He knew the plan had a hole in its funding, one the council now puts at more than £47m, and he put it to a vote anyway, without putting that hole in front of the people being asked to vote. Alton residents were sold a plan its own champion knew wasn’t financially viable, and the gap was only revealed six weeks later in a Cabinet paper.

Cllr Ayden Dikerdem speaking the Wandsworth Council Housing Committee
Cllr Ayden Dikerdem

Labour’s answer on the night was to ask the committee to recommend delivering the scheme as balloted, “unamended and unchanged”. The motion fell.

Cleaner estates, same complaint

The committee also heard how the council plans to buy estate cleaning for the next eight years and possibly sixteen, and the complaints about the current contract came with it.

Only 58.1% of tenants were satisfied with cleaning in 2024-25, the council’s own figures show, against a London median of 64.8%. Yet council inspectors give 98% of blocks a B+ rating, according to Thomas Glockner, vice-chair of the Borough Residents’ Forum. Having walked round with a cleaner, he said the inspection seemed like “a rigged process. It’s very difficult to fail”, and that the contract favours the contractors “in an almost ridiculous fashion”.

Under the new contract, price will count for 60% of the final choice of cleaner, while the average charge is set to rise from £6.58 a week in 2025-26 to £8.38 in 2027-28. The committee let the plan go to Cabinet without changes.

For Labour’s Cllr Sarah Davies, the Alton paper was “a bit wishy-washy”. “We’re six months in,” she told Cllr Corner, and she was finding it hard to get any assurance about what would actually happen.

Nor would Cllr Corner give one on the money from selling council homes. He would not write into the council’s new policy on sales a promise that the money raised goes on buying homes to replace them, saying the council needed flexibility. A Labour proposal to add it fell.

We put questions to the council, Cllr Corner and the committee’s chair, Cllr Chris Baron, yesterday, including why the figure cannot be published before Cabinet decides and whether Cabinet will wait for it. We also asked Cllr Dikerdem why the funding gap was not front and centre of what residents were shown. None had responded by the time of publication.

Twenty years, three plans, two administrations and one ballot on, the Alton has 55 homes on the way and a promise of phases with no dates. Roehampton has heard promises before. It is owed a timetable.

What happens next

Wednesday 9 December: the council’s Cabinet decides on the plan, including the Alton. Cabinet meetings are webcast at wandsworth.public-i.tv.

Late January: the Housing Overview and Scrutiny Committee is due to discuss the City Hall grant figure in public, once the embargo has lifted.

Write to: Cllr Matthew Corner, Cabinet Member for Housing, at cllr.m.corner@wandsworth.gov.uk, before Cabinet meets on 9 December.

Total
0
Shares
Leave a Reply

Your email address will not be published. Required fields are marked *

Related Posts
Total
0
Share