What’s actually happening to Wandsworth Bridge this summer – and why the official communications got so confused

Lane works start 26 May for five months. The council was slow to announce them.
Wandsworth Bridge northbound

Wandsworth Bridge loses lanes from Tuesday 26 May through autumn 2026 for a £2.35m scheme that makes the bus and segregated cycle lane permanent, narrows car lanes, rebuilds structural waterproofing beneath the footways that was left undone in earlier phases, and widens the pavements on both sides of the crossing.

Residents received the council’s first formal letter about the works this week, signed by Henry Cheung, Assistant Director of Engineering. It comes over a month since we first reported the works, having obtained the information from FOI documents on a separate issue rather than through any council announcement.

The works are certain to add even more congestion to an already overly congested Putney and come as Wandsworth Council faces questions over its lack of maintenance and budget of its bridges, including Putney Bridge, which scores below a level where engineers require work to be done.


Wandsworth Bridge: how the layout changes
Cross-section looking north. The deck stays the same total width — wider footways and cycleways mean narrower road lanes. Footway and cycleway widths confirmed; road lane widths illustrative.
Now — before works
Footway
Cycle lane
Traffic lane
Bus lane
Centre line
From autumn 2026 — after works
+1m each side: footway 1.5m→2m, cycleway 1.5m→2m
Widened footway
Widened cycle track
Traffic lane (narrowed)
Bus lane (narrowed, permanent)
Centre line
Total deck width unchanged. Road lane widths illustrative — exact narrowing unconfirmed. Footway and cycleway widths confirmed.
Sources: Wandsworth Council resident letter (Henry Cheung, 11 May 2026); Cllr Ethan Brooks relaying officer confirmation, WhatsApp 15 May 2026. Three-lane road configuration confirmed from Google Street View. Total deck width fixed — the 2m gain across footways and cycleways on each side is taken from the road lanes. Exact lane narrowing unconfirmed; widths illustrative. The councillors’ leaflet described existing provision as “a combined 3-metre pavement and cycle lane” — officers confirmed two separate 1.5m strips.

What is actually being built

The scheme has five components: a stepped cycle track on both sides of the bridge; widened and resurfaced footways; essential maintenance to the bridge deck; improvements to the Jews Row junction and Bridgend Road bus stops; and a full carriageway resurfacing at the end of the programme, which will require a one-week overnight closure between 9pm and 5am.

Two-way motor vehicle traffic will be maintained throughout the main works. The northbound bus and cycle lanes will be suspended while contractors are on the bridge. Pedestrian access is maintained, though routes may change.

The contractor is FM Conway, which will handle day-to-day works management. Once the works finish, the permanent layout will keep the northbound bus lane and one general traffic lane in each direction, with segregated cycling facilities on both sides and widened footways.

The 2021 trial that is now permanent

The bus lane and segregated cycle lane were introduced under a temporary traffic order in 2021, following refurbishment works on the bridge. A monitoring review conducted with TfL and the London Borough of Hammersmith and Fulham found that cycling levels increased by over 25%, while bus and road network performance remained stable, according to their figures.

A report presented to Wandsworth’s Transport Overview and Scrutiny Committee on 11 February 2026 confirmed: “The changes and associated traffic order have been made permanent.” That decision was on the public record three months before the current works were announced.

The £2.35m cost is split, according to figures circulated by the three Thamesfield ward councillors – through which more displaced traffic is now expected to flow – as £1.45m from the council’s capital budget and £900,000 from the Community Infrastructure Levy, paid by developers. The council has not yet confirmed those figures. What is confirmed, through Cllr Ethan Brooks’s own account from officers, is that the bulk of the cost is not for the bus lane or cycle track changes but for something deferred from an earlier phase: “structural and waterproofing works beneath the existing footways which were purposely omitted under phase 1 and 2 of the bridge remedial works.”

In other words, the repairs Phases 1 and 2 did not do are now the most expensive part of Phase 3. The pattern is familiar. Putney Bridge’s structural condition has been below the national threshold for action since at least December 2023, with the council aware of the problem throughout.

The disruption picture

From 26 May, three of south-west London’s four river crossings will be impaired simultaneously. Albert Bridge has been fully closed since February, following an inspector’s warning. Hammersmith Bridge has been closed since 2019. Meanwhile, Putney Bridge junction remains unremedied after the botched redesign 18 months ago. Wandsworth Bridge will add lane restrictions to that list from the end of the month.

What the councillors said

The lack of communication has impacted both residents and councillors alike, leading to significant confusion. In the same week as Cheung’s letter, the three Thamesfield Conservative councillors published a leaflet that described the scheme in a way that differed from the council on three significant points.

On the bus lane, the leaflet stated: “The separate bus lane will be removed and there will be one lane of traffic running north and south.” The council’s letter says the opposite: the northbound bus lane is being made permanent. The Transport Committee paper confirmed that decision publicly in February.

On the pavements, the leaflet described the existing provision as “a combined 3-metre pavement and cycle lane” being replaced with “a 2-metre pavement and a 2-metre cycleway.” The implication was of narrowing. Cllr Brooks subsequently clarified, relaying officers’ confirmation: “No pavement narrowing. The existing pavement width on each side is 1.5m footway + 1.5m cycleway. The new width will be 2m + 2m.” The only practical explanation for that is that the car lanes with be narrowed further.

On the cost, the leaflet placed the £2.35m figure under the question “How much is all this costing?” immediately after its description of the bus lane removal, framing the cost as covering the lane changes. Brooks corrected that interpretation the morning after distribution: the cost is driven by the deferred structural waterproofing, rather than £2.35m being the cost of the bus lane removal.

Councillors are due to be briefed on the scheme this coming Monday, with the approvals and approach seemingly decided by officers during the election period.

The pattern

The communication failures around this scheme are not isolated. The council held onto the works for six weeks before formally writing to residents. The first formal letter arrived less than two weeks before the works start. The ward councillors’ written description of their own constituency’s biggest transport change of the summer got the headline facts wrong.


Three of five crossings impaired this summer
Status of the five south-west London Thames crossings between Hammersmith and Chelsea, May 2026
Hammersmith Bridge
Closed to all traffic since 2019. No confirmed reopening date for motor vehicles. Pedestrians and cyclists permitted on a managed basis.
Closed
Putney Bridge
Open, but structural condition below the national-guidance threshold for action. Council aware since December 2023. Junction redesign still unremedied. No confirmed repair timeline.
Structural concern
Wandsworth Bridge
Lane restrictions from 26 May 2026 through autumn 2026. £2.35m scheme widens footways, makes bus and cycle lanes permanent, and rebuilds deferred structural waterproofing.
Lane works from 26 May
Battersea Bridge
Open. Currently serving as a diversion route for Albert Bridge traffic. Status confirmed open as of May 2026; no major works or restrictions reported.
Open
Albert Bridge
Fully closed since February 2026 following inspector warning. Expected to remain shut for up to a year.
Closed
Closed to motor vehicles
Lane restrictions / works
Structural concern
Open / no restrictions
Sources: Putney.news reporting, April–May 2026. Hammersmith Bridge: closed since August 2019. Putney Bridge structural condition: Putney.news, 12 May 2026, citing council inspection records from December 2023. Wandsworth Bridge: works start 26 May 2026 per Wandsworth Council resident letter (Henry Cheung, 11 May 2026). Battersea Bridge: open and confirmed as active diversion route for Albert Bridge closure per Wandsworth Council statement, February 2026; no restrictions identified as of May 2026. Albert Bridge: closed February 2026 following TfL inspector warning; expected closed for up to a year.

The wider picture that Wandsworth Bridge now joins is one of deferred maintenance accumulating across multiple crossings simultaneously. We have documented the pattern across all four crossings: structural problems identified, repairs postponed, costs rising when the bill eventually arrives. Wandsworth Bridge’s Phase 3 is the latest and most visible instalment.

Total
0
Shares
Leave a Reply

Your email address will not be published. Required fields are marked *

Related Posts
Total
0
Share